Original ASTRID2 Plan
Description | Date |
Time period for Infrastructure Grant | August 2009 - February 2013 |
ASTRID2 Milestones |
|
ASTRID2 design report review | September 2009 |
Magnets and power supplies ordered | November 2009 |
Detailed layout of ASTRID2 vacuum system | May 2010 |
Magnets and power supplies delivered | November 2010 |
Beam circulating in ASTRID2 | September 2011 |
First user beam on 1st monochromator on ASTRID2 | March 2012 |
All beamlines in operation on ASTRID2 | March 2013 |
ASTRID |
|
ASTRID extraction kicker designed | June 2009 |
ASTRID extraction kicker ordered | August 2009 |
ASTRID extraction kicker installed | November 2010 |
Dark period on ASTRID to commision kicker | December 2010 - January 2011 |
Synchrotron light time shared with ASTRID2 | March 2011 - June 2012 |
Last sychrotron light in ASTRID | June 2012 |
Transfer beamline |
|
Transfer beamline design completed | September 2009 |
Components for transfer beamline ordered | December 2009 |
Installation of transfer beamline | November 2010 - January 2011 |
Commissioning of transfer beamline with beam | February 2011 - March 2011 |
ASTRID2 |
|
ASTRID2 design completed | July 2009 |
Design DC magnets for A2 | July 2009 - August 2009 |
Order DC magnets for A2 | September 2009 |
Design pulsed magnets and supplies for A2 | July 2009 - August 2009 |
Order pulsed magnets and supplies for A2 | September 2009 |
Design DC power supplies | July 2009 - September 2009 |
Multipole wiggler design completed | November 2009 |
Order DC power supplies | December 2009 |
Magnets and supplies for ASTRID2 delivered | November 2010 |
Commissioning of A2 with beam | March 2011 - September 2011 |
Synchrotron light time shared with ASTRID | March 2011 - June 2012 |
Multipole wiggler delivered/installed | May 2011 |
First synchrotron light from ASTRID2 | October 2011 |
Undulator installed in ASTRID2 | November 2011 |
Beamlines |
|
Transfer of SX700/SGM1 | April 2011 - September 2011 |
Commissioning of SX700/SGM1 with beam | October 2011 - November 2011 |
Transfer of SGM2 | July 2011 - December 2011 |
Commissioning of SGM2 with beam | January 2012 - February 2012 |
Transfer of SGM3 | November 2011 - April 2012 |
Commissioning of SGM3 with beam | May 2012 - June 2012 |
Transfer of UV1 | April 2012 - September 2012 |
Commissioning of UV1 with beam | October 2012 - November 2012 |
Transfer of CD1 | July 2012 - December 2012 |
Commissioning of CD1 with beam | January 2013 - February 2013 |