ASTRID2 Time Line
Description | Date |
Time period for Infrastructure Grant | August 2009 - February 2014 |
2009 |
|
ASTRID extraction kicker designed | June 2009 |
Design DC magnets for A2 | July 2009 - August 2009 |
Design pulsed magnets and supplies for A2 | July 2009 - August 2009 |
Design DC power supplies | July 2009 - September 2009 |
ASTRID2 design completed | July 2009 |
ASTRID extraction kicker ordered | August 2009 |
Transfer beamline design completed | September 2009 |
ASTRID2 design report review | September 2009 |
Order DC magnets for A2 | September 2009 |
Order pulsed magnets and supplies for A2 | September 2009 |
Magnets and power supplies ordered | November 2009 |
Multipole wiggler design completed | November 2009 |
Components for transfer beamline ordered | December 2009 |
Order DC power supplies | December 2009 |
2010 |
|
Detailed layout of ASTRID2 vacuum system | May 2010 |
Installation of transfer beamline | November 2010 - January 2011 |
ASTRID extraction kicker installed | November 2010 |
Dark period on ASTRID to commision kicker | December 2010 - January 2011 |
2011 |
|
Multipole wiggler delivered/installed | June 2011 |
Commissioning of transfer beamline with beam | June 2011 |
Magnets and power supplies delivered | July 2011 |
2012 |
|
Radiation wall completed | May 2012 |
Commissioning of A2 with beam | May 2012 - September 2012 |
Beam circulating in ASTRID2 | August 2012 |
First synchrotron light from ASTRID2 | December 2012 |
Transfer of UV1 | December 2012 - January 2013 |
2013 |
|
Transfer of SX700/SGM1 | January 2013 - April 2013 |
Commissioning of UV1 with beam | February 2013 - May 2013 |
Transfer of SGM3 | February 2013 - August 2013 |
Undulator installed in ASTRID2 | February 2013 - March 2013 |
Commissioning of SX700 with beam | March 2013 - June 2013 |
First user beam on 1st monochromator on ASTRID2 | April 2013 |
Transfer of SGM2 | June 2013 - September 2013 |
Commissioning of SGM3 with beam | August 2013 - November 2012 |
Commissioning of SGM2 with beam | September 2013 - December 2013 |
Last sychrotron light in ASTRID | October 2013 |
Transfer of CD1 | November 2013 - March 2014 |
2014 |
|
Commissioning of CD1 with beam | April 2014 - July 2014 |
All beamlines in operation on ASTRID2 | July 2014 |