ASTRID2 Status

2015

 
24-26 March   Installation of the Landau Cavity and modification of ASTRID2 bumper 3.

2014

 
27-29 October   Modification of ASTRID2 bumper 2.
22-24 September   AU-IR beam line installed.
18-20 August   Modification of ASTRID2 bumper 1.
11th August   First users on the AU-CD beam line.
12th May   First users on the MatLine and SGM3/ARPES beam lines.
9th May   The AU-CD beam line has been installed on ASTRID2 and is under vacuum.
22nd April   CD1 is the final beam line to be removed from ASTRID.

2013

 
2nd December   First external user of ASTRID2 on the AU-UV beam line.
11th September   First User Beam. Commissioning of the AU-UV beam line starts, first spectrum recorded.
9th September The design current of 200 mA has now been stored in ASTRID2. Top-up operation at 200 mA succesful.
28th August Installation of the old ASTRID undulator (WUN131) in ASTRID2
23rd August   186 mA accumulated in ASTRID2
16th July Installation of the AMO undulator (WUN121) in ASTRID2
12th July   Closed WIG121 (Multipole wiggler) to 13 mm with beam in ASTRID2. No degredation in injectino efficiency. A small chamber alignment error prevented closure of the gap to the noiminal 12 mm.
11th July   Stable top-up operation at 90 mA. The limit is still due to high temperatures in the bumper magnets despite upgrades.
11th June   FMH111 bumper upgraded with better chamber transitions and cooling
14th May First light in a beam line. With only 1 mA of stored beam in ASTRID2 opened up the A2-UV1 beam line for initial tests.
30th April   FMH121 bumper upgraded with better chamber transitions and cooling
16th April   FMH161 bumper upgraded with better chamber transitions and cooling
6th February   The first beam line is now attached to ASTRID2. The final section of beam pipe for A2-UV1 was installed and the whole beam line is now under vacuum.
1st February   155 mA accumulated current in ASTRID2.
7th January   100 mA current stored in ASTRID2 for the first time!

2012

 
14th December The new 2.5m undulator for the AMO beamline was delivered
12th December   A stored current of 36 mA in ASTRID2.
2nd November The first stored beam with RF in ASTRID2! It was also possible to accummulate beam in the new ring.
10th September The official opening of ASTRID2 by Morten Østergaard, the Danish Minister for Research, Innovation and Higher Education.
7th August The electrons injected into ASTRID2 can now circulate the ring more than 1300 turns (200 microseconds).
10th July First full turn around the ring!
29th May The beam is now half way around the ring.
14th May First beam in ASTRID2.
13th May First beam through the transfer beamline.
11th May RF Cavity for ASTRID2 has been delivered and installed.
10th May The radiation wall around ASTRID2 is almost finished.
26th April   The transfer beamline between ASTRID and ASTRID2 has been completed and is under vacuum.
25th April The radiation wall starts to go up around the ring.
20th April   All of the girders for the ASTRID2 ring are now under vacuum and have been baked.
6th February   Half of the ASTRID2 ring is now under vacuum and has been baked. Section 2 bakeout was completed today, section 3 baking will start this week.

2011

 
2nd November   Section 1 of ASTRID2 is now being baked.
21st October   First vacuum! Section 1 of ASTRID2 is now under vacuum.
20th September   The concrete blocks which will be used to build the radiation shielding are being placed in the basement.
26th August   Installation of the power cables for the dipole and quadrupole magnets commenced.
21st July   First section of the transfer beamline under vacuum, in preparation for further extraction diagnostics.
20th July All girders for the ring have now been installed
6th July   First extraction of beam with ASTRID running in booster mode (22 second cycle time)
29th June The first girder for the ring has been installed. Girder 2 has been placed on its supports.
28th June First two girders for ASTRID2 delivered today
28th June The first extracted beam from ASTRID
20th June The multipole wiggler was delivered
April/May The magnets for the transfer beam line were installed
23rd March Supports for the magnet girders were put in place.
24th February   Gate valves for the ring were delivered.
18th February   The ion pumps for the ring were delivered
February Utilities required for the ring are being installed.
7th January   Gate valves for ASTRID2 ordered
January The ASTRID2 ring hall is empty and construction on the podium has started

2010

 
8th December   Ion pumps for ASTRID2 ordered
6th December   Main dipole chambers for ASTRID2 ordered
2th December   Extraction kicker for ASTRID received
February   Order of main power supplies for ASTRID2
January   Multi Pole Wiggler (MPW) for ASTRID2 ordered

2009

 
7th September   Girders with magnets for ASTRID2 ordered
7th September   Fast magnets with power supplies for ASTRID2 ordered
August Preliminary design report for the ASTRID2 ring sent out for review.
January   Design of ASTRID2 started

2008

 
December 2008   ISA awarded money to build ASTRID2
     
     

Construction

Current Status as of Friday 4th Janaury 2013: All of the ring is now under vacuum and has been baked. The RF cavity has been delivered and installed. Commissioning of the ASTRID2 ring is well underway with currents of around 30-40 mA stored.


By clicking on one of the links below you can view a video showing the construction progress of the ring. There is a short 20 second film which shows the complete construction of the ring from the beginning of 2011, when the ring hall was empty, until the ring was enclosed with a concrete wall in May 2012. The longer films show the daily progress of the construction and have been split into separate files according to year. The film for 2012 was last updated: 15th May 2012. The 2011 film shows the progress of the building of ASTRID2 throughout 2011. Some of the files are quite large.


.avi (mpeg4) file

.mov file Quick time

.wmv file Windows Media Player
20 Second film 20 Second film 20 Second film
2012 to 15th May 2012 to 15th May 2012 to 15th May
2011 2011 2011

Below you will find a selection of photographs showing the progress with ASTRID2. Click on a thumbnail to view the picture in a larger version

December 2010
 
3rd January 2011
 
12th January 2011
 
4th February 2011
 
23rd March 2011
 
April/May 2011
 
20th June 2011
 
28th June 2011
 
28th June 2011
 
29th June 2011
 
20th July 2011
 
8th March 2012
 
25th April 2012
 
10th May 2012
 
11th May 2012
 
11th May 2012
 
13th May 2012
 
14th May 2012
 
29th May 2012
 
10th July 2012
 
7th August 2012
 
10th September 2012
 
2nd November 2012
 
26th November 2012
 
14th December 2012
 
15th May 2013
 
16th July 2013
 
28th August 2013
 
     
9th September 2013
 
     

 

 


Last Modified 11 October 2018

 
ISA

Centre for Storage Ring Facilities
Department of Physics & Astronomy

Aarhus University

Ny Munkegade 120
8000 Aarhus C

E-mail: isa@phys.au.dk
Tlf: 8715 0000


CVR-nr.: 31119103
Momsnummer/VAT: DK 3111 9103
P-nr.: 1009828059
EAN-nr.: 5798000419872
Stedkode: 2902
Enhedsnummer: 5710

About us

  • Profile
  • Employees
  • Contact us

Degree programmes

  • Bachelor
  • Master
  • Engineering
  • PhD



© — Cookies at au.dk
Privacy policy
Web Accessibility Statement