ISA meeting
Week 5, January 29, 2002.
Status of the ring: During the past week, we had some problems with the RF system during injection. Yesterday, we discovered, that the problem may be caused by the RF plunger
motors getting stuck at certain positions. We have spares, and will replace the motors as soon as possible. This will hopefully lead to easier and faster injections and higher stored
currents.
Beamlines: All beamlines are reported to be running well. The detailed schedule for this run has now been made. It is posted on the www. You can reach it via our schedule page, or
go directly to this page: http://www.isa.au.dk/schedule/02SRRun.htm
29/01 2002 /
+