ISA meeting
Week 16, April 17, 2001.
Status of the ring: The ring has been running well during the Easter vacation, but due to some problems with the microtron, the current was lower than usual the last couple of days.
Part of the problem has been solved, but there is still some instability in the microtron. We are looking for the cause, but we will in any case be able to provide beam in this week,
which is the last of this run.
The present run will end on Monday April 23 at 08:00, the following week will be used for the changeover to Ion Run 1/01, which will start in week 18, i.e Monday April 30. The
schedule for the coming ion run may be seen on http://www.isa.au.dk/schedule/2001ionrun1.htm .
On next Tuesday, April 24, we plan to have an informal meeting, in which results obtained in this SR-run will be presented. There should be one brief (max. 15 min) presentation
from each beamline. The purpose is mainly to inform all of us about the many activities at ASTRID. The meeting will take place in 525-323 on Tuesday April 24 12:30 to 14:00.
Everybody is welcome!
17/4 2001 /
+